Georgian Sustainable Urban Transport Investment Program, Final Environmental Monitoring Report (EMR) for SUTIP 1

March 12, 2018
Donor: ADB

Sustainable Urban Transport Investment Program SUTIP 1 (ADB Loan - 2655 -GEO) aims at development of the efficient, reliable and affordable urban infrastructure and service improvement in Georgia.

 

Final Environmental Monitoring Report for the projects implemented under the Tranche 1 of the SUTIP, has been prepared by the Municipal Development Fund and covers the period of July-December, 2017.

 

Separate Post-Construction Environmental Audit reports have been prepared for Tranche 1 sub-projects:

   -   Tbilisi Metro Line 2 and Creation of University Station;

   -      Anaklia coastal improvement  (Phase 1).

 

Post-construction Environmental Audit Reports are attached to this Final Environmental Monitoring report as a separate attachments - Attachment 1 and Attachment 2.

 

Attach. 1 POSTC_REPORT_JULY__Metro

 

Attach. 2 Post Construction Environmental   report _Anaklia

 

SUTIP  T1_EMR_July-December, 2017-Final