Rehabilitation of Kobuleti Seawall

April 28, 2017
Municipality: Kobuleti
Donor: WB

The Sub-project„Rehabilitation of Kobuleti Seawall“, is being implemented under the Second Regional and Municipal Development Project (RMIDPS) supported by the World Bank. The SP envisages dismantling of the old protection wall and arranging instead coast protection stepped wall with the length of 1900 meters and improvement of the boulevard site in the coastline of Kobuleti City.

 

On April 27, 2017 at 15:00, a Public consultation meeting was held in Kobuleti Municipality Governance (Gamgeoba), (N141 Davit Aghmashenebeli Avenue, 6200 Kobuleti, Georgia) regarding Environmental and Social Management Plan and social accountability issues of the Subproject.

                                                                                                                  

The Environmental and Social Management Plan of the Subproject is available at the following link:

   EMP_KobuletiSeawall-eng