The third stage of works for the arrangement of the water supply system serving five villages in the Gardabani Municipality

July 12, 2022
Municipality: Gardabani
Donor: WB

 The Sub-project – „The third stage of works for the arrangement of the water supply system serving five villages in the Gardabani Municipality, is being implemented under the Second Regional and Municipal Development Project Additional Financing (SRMIDP-AF) supported by the World Bank. The sub-project (SP) aims to arrange the water supply system which will serve five villages in the Gardabani Municipality.

 

On May 21, 2021, a public consultation meeting was conducted online through Zoom application due to the pandemic situation in the country.

 

The Environmental and Social Management Plan of the Subproject is available at the following link:

ESMP_Gardabani water supply _ 2022_04_07